MSD Wastewater Collections Maintenance Shop

Location: Cincinnati, Ohio

Delivery Method: GC

Industry: Municipal

Architect: Burgess & Niple

Mechanical Engineer: Advanced Engineering Consultants

Civil & Structural Engineer: Burgess & Niple

Universal Contracting served as the General Contractor for the MSD Wastewater Collections Maintenance Shop project. The work included the construction of a new maintenance bay and office addition, along with significant upgrades to the existing facility to improve operational efficiency and functionality.

The project scope included roof demolition and replacement, HVAC system upgrades, electrical system up dates, and interior renovations to support maintenance operations and administrative functions.

The work included:

  • Site utilities
  • Concrete foundations
  • Pre-engineered metal building (PEMB) and new roof system
  • HVAC and controls
  • Electrical, security, and fire alarm systems
  • Plumbing and fire suppression
  • Interior finishes
  • Exterior site work

Completed in approximately 390 days with a $3.55 million construction value, this project reflects Universal’s ability to deliver complex municipal facility upgrades that integrate new construction with renovations to active infrastructure environments.

Architect: Burgess & Niple

Mechanical Engineering: Advanced Engineering Consultants

Civil & Structural Engineering: Burgess & Niple

More Projects

Partner With Us

Send Us A Message