Location: Mason, Ohio
Delivery Method: GC
Industry: Educational
Architect: VSWC
Mechanical Engineer: IMEG Corp.
Structural Engineer: GOP Limited
Description:
Universal Contracting served as the General Contractor for a 6,000-square-foot addition to Mason Intermediate School, along with the interior renovation of two innovation hubs. The project enhanced the school’s learning environment through expanded instructional space and modernized collaborative areas.
The addition consisted of a masonry structure with brick veneer and a sloped shingled roof supported by metal trusses. Interior finishes included epoxy restroom flooring, carpet, ceramic tile, casework, and operable glazed wall systems.
The project scope included:
- Self-performed concrete foundations
- Concrete slab-on-grade
- Sitework, excavation, and site utilities
- Plumbing
- Structural masonry
- Landscaping
- Flooring
- Painting
- Mechanical and electrical systems
- Framing, drywall and acoustic finishes
- Self-performed doors, frames, and hardware
- Interior demolition
The project was completed over an 11-month schedule, with a final completion date of August 7, 2023, reflecting Universal’s ability to deliver phased additions and renovations within an active educational environment.